Chartrange were appointed by Willmott Dixon in October 2021 by Willmott Dixon to carry out remediation works to Stockport Bus Station. The site has been earmarked for development by Transport for Greater Manchester to serve as the all new Stockport Interchange.

The transport interchange will feature an innovative two-acre rooftop park which will improve leisure and recreation opportunities in the town centre and create more green space for everyone to enjoy. The park is expected to encourage wildlife and biodiversity as well as provide a safe environment for people to meet and relax.

Beneath the unique rooftop park, there will be a fully accessible, covered passenger concourse in the interchange with seated waiting areas, cycle storage facilities and 20 bus stands, providing capacity for future growth in bus services.

It will also provide new cycling and walking routes to the train station, Trans Pennine Trail and town centre.

Scope of works

Removal of Soft Landscaping
• Inclusive of shrubs, top soil and root balls

Breaking Up Hard Surfacing
• Inclusive of tarmac, bitumen paving, concrete, PCC paving, kerbs and foundations

Earthworks
• Excavate to reduced level
• Cart surplus material off site
• Fill to make up levels
• Level and compaction

Bulk Excavation
• Excavation 20,000m3
• Crushing and screening to create suitable fill material, breaking out obstructions,
segregating and sorting site won material for re use in layers. Compact in 150mm layers to achieve required CBR grading
• Removal of surplus material off site

Piling Mat
• 600mm deep, site crushed material, 6F5 stone, level and compaction, two layers of TENSAR TX 160 geogrid installed.